Hwy 86 Sewer Ph 1


07:10am- Picking up cylinders to take to Springfield to lab from pour last week on grouting of floors. 
Spoke to Junior w/ FlatCreek and told him about following contour when tar is applied to basin. Text John Escobar to remind him of the same!
I do not know if they are working here to day as no one has said fore sure yet. 

10:23am- Asphalt coating and rollers have been dropped off. Someone is to be here anytime now to begin. 

12:39pm- Caleb is now onsite to begin coating the walls. John was onsite and went over approach with Caleb. 

13:28pm- After sweeping bottom edge of wall off, asphalt coatings begin. 

14:03pm- Chalk lines on North and South walls are done. 

15:01pm- 1st coat on East and South walls now. 



14:26pm- 1st coat all the way around now completed. 

2nd coat begins at this time. 

17:13pm- 2nd coat is done from east wall around including west wall now!

17:46pm- Caleb is now done with second coat to this point. 