Hwy 86 Sewer Ph 1
07:10am- Picking up cylinders to take to Springfield to lab from pour last week on grouting of floors.
Spoke to Junior w/ FlatCreek and told him about following contour when tar is applied to basin. Text John Escobar to remind him of the same!
I do not know if they are working here to day as no one has said fore sure yet.
10:23am- Asphalt coating and rollers have been dropped off. Someone is to be here anytime now to begin.
12:39pm- Caleb is now onsite to begin coating the walls. John was onsite and went over approach with Caleb.
13:28pm- After sweeping bottom edge of wall off, asphalt coatings begin.
14:03pm- Chalk lines on North and South walls are done.
15:01pm- 1st coat on East and South walls now.
14:26pm- 1st coat all the way around now completed.
2nd coat begins at this time.
17:13pm- 2nd coat is done from east wall around including west wall now!
17:46pm- Caleb is now done with second coat to this point.