Hwy 86 Sewer Ph 1
07:16am- Pump truck and crew arrives for floor pouring of grout today!
07:30am- Concrete tested with Air:7%, Slump 5”, Temp: 60*F. 4 cylinders made. 50 yds ordered.
07:59am-Pour is going well!
08:54am- Floor near done!
09:00am- Done!
09:13am- Wet Well grout begins.
09:32am- Grout in wet eell, but needs to set a bit to shape it.
10:34am- Wet well completed!
10:49am- Crew in AWWOB now working floor grout to put final “smooth” finish to it!
11:17am- AWWOB floor now completed!
11:22am- This is the last bit of form to be removed!
Basin is done!
11:56am- Crew is to be done here by 14:00pm- I will ne headed offsite now.