Hwy 86 Sewer Ph 1


07:12am- Inside forms have all been removed except for in the wet well. It all looks pretty good so far!







08:12am- Crew starting to show up this morning to continue pulling forms. 


-I will be in a WebX training meeting today, but will be available if there should be questions or concerns. 

15:00pm- Meeting over. 9am to 3pm. 

Floor crew came and set grade puns in floor this afternoon. Pour is scheduled for 7:30am tomorrow morning. 

Chalk lines established on walls! There is an approximate 2% slope based on conversation that T RSD and I had about a cost saving by not adding the two feet upon the walls. Floor Contractor said today it should save about half; 60 + yards. 

Walls looking pretty decent! Forms still coming from North and east walls along with wet well forms still coming out. 

17:39pm- Wet well is now cleared of forms. Cleaning out bottom will now occur so that floor crew can pour it tomorrow. 

18:10pm- End of the day!