Hwy 86 Sewer Ph 1
07:40am- Crew onsite to finish installing bracing this morning. Pour scheduled still for 14:00pm.
10:35am- Crew has bracing up and are currently setting grade inside of forms.
12:28pm- Now awaiting pump truck! All is good to go now!
14:14pm- Still awaiting Pump Truck arrival!
14:52pm- Pump truck now arrived!
15:31pm- pour begins!
Concrete tested and cylinders made. Air:4.5%, slump: 6”, temp: 62*F.
16:53pm- Crew steadily working!
18:12pm- Nearing completion! Approaching 120 yds
A total of 12 cylinders made today!.
18:59pm- Waiting on a 5yd call back!
19:32pm- NOW we are even closer to being done!
19:40pm- Completed! Just some top finish work now…
-20:18pm- crew is now packing up! Done onsite for today!
Comments
Post a Comment