Hwy 86 Sewer Ph 1


07:40am- Crew onsite to finish installing bracing this morning. Pour scheduled still for 14:00pm. 

10:35am- Crew has bracing up and are currently setting grade inside of forms. 

12:28pm- Now awaiting pump truck! All is good to go now!

14:14pm- Still awaiting Pump Truck arrival!

14:52pm- Pump truck now arrived!

15:31pm- pour begins!

 Concrete tested and cylinders made. Air:4.5%, slump: 6”, temp: 62*F. 
16:53pm- Crew steadily working!

18:12pm- Nearing completion! Approaching 120 yds
A total of 12 cylinders made today!.

18:59pm- Waiting on a 5yd call back!

19:32pm- NOW we are even closer to being done!
19:40pm- Completed! Just some top finish work now…


-20:18pm- crew is now packing up! Done onsite for today!