Hwy 86 Sewer Ph 1


07:21am- Crew is back to work on south side of AWWOB today. 

08:23am- All material pulled from east bank and taken to south side. 

Had dozer recut area here to get rid of sticky material now. 

South side is about done for now. 

08:55am- Rest of basin up to chalk line will have two coats of asphalt tar applied today. No more backfill until Monday when second break on cylinders will occur. 

I will be off this site and headed to Tower Rd. 

09:15am- Lid on MH A2 will be set in diamond and pitched with roadway today. 

09:28am- Fire Station #4 here on Devils Pool Rd is getting tied in today! Tank has been pumped and collapse is taking place. 

10:12am- Forming of diamond around lib is underway as concrete to arrive soon. 

11:13am- Concrete has begun and rebar has been placed. 



12:44pm- Poured 

13:17pm- Fire station is tied to sewer and around corner!





13:49pm- Cleanout is cut in line now to make run compliant!

I will be headed offsite now!