Crew will be working today to keep clearing going and bring in new material from different site from Arena area that they will be digging out today. 
07:39am- Equipment now onsite and removal of top layer is underway. 

08:53am- More gravel is placed this morning while we await the dry fill to be hauled in. 

10:02am- Loads are now coming in!

Alot of rock in this fill so its looking up for good backfill material!

10:22am- Filling against the nluff to get dirt laid out easier. 

10:53am- Tower Rd work will start again today. MH A2 will get readjusted along with a diamond shaped concrete square around it. Grading work and overall cleanup too occur. 

11:24am- Another look at East side of basin. 

11:48am- Sheep’s foot making passes. 

13:35pm- More compaction occurring!

Dozing in lifts on north end side. 

14:06pm- Small compactor making passes on north side. 

16:43pm- Fill has stopped on East and North sides until next week after another cylinder break occurs. 

 South side is getting the attention now!

17:09pm- Crew has called it a day. Working tomorrow on south side only to half way point. 