Hwy 86 Sewer Ph 1


07:12am- Crew having discussion on clearing possibly today as well as continuing gravel backfill on AWWOB. 

7:57am- Dozer cutting banks to allow for gravel placement. 



Compactor in use now. 

09:37am- More gravel going in!



10:09am- Clearing begins today for force main from AWWOB. 

11.12am- East wall has more gravel now. 

12:33pm- Crew is calling it a day due to the constant mist of rain making it to sticky to continue. 
Clearing will continue though at this moment.
-Spoke with John Escobar with my concerns about the dirt that came off site not being suitable for north and east wall sections due to it being deleterious type material. He understands and said he would look at it later today a make a decision. 