Hwy 86 Sewer Ph 1


07:54am- Crew has made it to the site to continue with wall form work today. String lines and bracing, along with walk boards getting installed. 

09:09am- Closing up wall between tall and short. Platform bracing going on walls. 


-I will be heading offsite at 10:00am for a meeting at the Branson office w/ Bryan and James. Be back onsite after lunch. 

14:00pm- Back onsite! Crew still placing bracing and getting forms straight. 

16:51pm- Crew packing things up to call it a day! Pour scheduled for 2pm tomorrow!