Hwy 86 Sewer Ph 1
07:14am- Crew is on schedule to pour this morning here at the Arena L.S. Mix design has been approved.
08:17am- Additives to be placed here onsite.
08:39am- Both trucks here. Additives have been mixed into concrete and 1st truck begins pour.
09:25am- Pour is right at being complete.
4-Cylinders were made after testing. Air: 4.75%, Slump 7” with Super P added, Temp: 68* F.
11:18am- Floor tie in bars and water stop and all good now. Crew is heading off site as well as myself.