Hwy 86 Sewer Ph 1
07:00am- No one onsite.
08:10am- Crew arrived at 07:55and I went over bar lengths with them for tying in floor and showed them where Bench Mark was for elevation. I will be offsite now for a visit to another job in Forsyth.
10:34am- Back onsite!
12:50pm- Panels are up on East and North sump walls.
South and West walls will be getting “L” bars placed through forms to tie to floor.
16:38pm- Floor tie in points are established on south and west walls of pit. Continued bracing will round out the day.