Hwy 86 Sewer Ph 1
08:04am- Crew showed up this morning at 07:50am.
Forms are being carried down to site now.
10:22am- More rebar being tied with forms now stacked inside.
12:27am- Rebar is mostly tied for sump area. Forms will start going up.
14:20pm- Inside toe boards are going in and corners squared.
16:31pm- Forms are still going in as more continue to be carried down.
16:58pm- Crew is wrapping up for the day!