Hwy 86 Sewer Ph 1
07:28am- Crew arrived at 07:15am to finish tying bar this morning.
07:48am- Steel temps are good! Pour still scheduled for 09:00am.
09:50am- 1st test low on air! Air is being added. 2nd test air now at 5.5%! 4 cylinders made.
10:34am- All is going well!
10:56am- 2nd set of cylinders pulled and 90 yds now in place!Air 6%.
12:57pm- Waterstop now being placed down into concrete.
14:00pm- Pour is finished for today; 130yds placed!
A total of 12 cylinders taken!