Hwy 86 Sewer Ph 1


07:19am- Crew onsite!

08:17am- Another bundle of rebar was pulled down for placement. Crew are cleaning rebar as they go. 

09:23am- Still tying floor top mat!

10:32am- Bar tying around pit area in forms. 


10:45am: I will be offsite to go to Judicial Center job. Be back ASAP. 

12:34pm- Back onsite with crew now placing vertical bars for walls. 

13:21pm- Wall bars still getting thread in place. 

14:23pm- More uprights to go in at every six inches now on short walls. 

15:34pm- Still tying uprights. Water stop will be dropped down once all uprights are in. 

16:02pm- Crew has called it a day. Not very much left to do. Pour is scheduled for Monday around 9:00am!