Hwy 86 Sewer Ph 1


07:18am- Concrete Floor crew starting to show onsite. Goal today is to get steel laid out and tied for floor!

08:07am- Forms have arrived and crew preparing to unload them. 

10:06am- Area is squared up and forms are taking shape!

11:23am- Rebar is getting placed and tied now!

12:46pm- Progress!

13:36pm- Crew now starting layout for top-mat chairs. 


13:42pm- I will be headed offsite to Judicial Center job. Be back ASAP. 

16:00pm- Back onsite as hail is falling! Crew is gone si not sure exactly what time they left-