Hwy 86 Sewer Ph 1
07:11am- As of yesterday evening, rock backfill against pit walls to occur today, but no one onsite yet…
08:20am- Gravel begins showing up this morning!
10:57am- 3 loads of clean rock has now been delivered…
11:06am- Placement of gravel around pit walls begins.
11:38am- Gravel is being pulled out to layers and vibratory compacted.
11:58- Compactor making passes.
-12:10pm- I meed to make a trip to Judicial Center job. Be back ASAP.
14:28pm- Back onsite with no crew here. Awaiting more gravel now to be dropped so they can continue
With the backfill process.
15:29pm- Gravel getting placed again!
16:51pm- 10 loads of gravel hauled by dump truck total and two loads now from haul truck!
17:14pm- Well, now they are on a time constraint to get this done as the concrete crew has been told they can start in the morning tying rebar for this floor…
18:00pm- Crew still going at it…
18:45pm- Crew is done and calling it a day!