Hwy 86 Sewer Ph 1
07:05am- No crew onsite at this time.
07:43am- Called FlatCreek and stated it was to nice out to not be working here at LS site! Rock is now on its way here so pad for floor of basin can be laid out today.
09:24am- Gravel has finally arrived along with a man to begin coating walls with water proofing!
09:51am- Asphalt coating being applied!
10:24am- 2 coatings are now applied!
12:15pm-Layout begins for edge of gravel.
13:09pm- Top of wall grade is shot and gravel begins going down!
14:08pm- Grade is getting checked on gravel being placed.
15:28pm- Another load of rock is coming yet today as operator is getting grade pretty close!
16:32pm- Pad is built, but rock has to go in around pit tomorrow! Operator is done for today here.