Hwy 86 Sewer Ph 1


07:52am- I’m onsite now after running cylinders to Springfield to lab. 
08:01am- Concrete crew is onsite and pulling forms on outside walls. 

09:31am- Concrete looking good!

11:43am- Forms now off and hopefully this rebar and additional forms to be moved this afternoon so gravel backfill can begin along with floor work. 




I will be offsite for a run to the Judicial Center job. 

13:52pm- Back onsite as the last of the forms along with all the rebar is being moved. 

14:12pm- Site is now ready for clean rock to be brought in. Concrete crew is now leaving site. 
Water proofing material to be applied to walls before gravel goes in. Junior w/FlatCreek is aware of this and is checking on getting someone here to do this yet today. 


15:15pm- Finally heard back from FlatCreek and they will have to get materials from Springfield, so nothing more to be done here today!