Hwy 86 Sewer Ph 1


06:48am- Crew to be onsite today to start setting forms



07:30am- Contractor onsite with questions on rebar placement in corners of 16”walls. Contacted Jacob and Spencer to get things worked out. We are now good to go!
08:18am- Rebar is dropped for rest of basin. 


-Offsite between 8:30am- and 10:45am

10:56am- crew getting uprights tied in place and chalk lines for “square”. 

14:05pm- More questions coming from crew, but they are getting addressed appropriately. Overlapping is an issue as some bars are way longer than necessary on the corners.

16:46pm- Tying process is of course slow, but going well now. This will round out the day. 