Hwy 86 Sewer Ph 1


07:16am- Crew here will be making tie in at MH A04 today. 

07:50am- Rock breaking continues here at Arena LS today. 

09:20am- Force main now tied to MH A04. 

09:48am- Now ready for thrust blocking. 

10:15am- Saw cutting control joints now starting on driveway at Fire Dept. 

10:40am- Thrust block now poured on fittings at tie in. 

11:01am- Saw cuts nearly completed. 

11:38am- Riser, ring and lid are on top of MH A04 now. Backfill begins. 

11:50am- Changing out operator on breaking rock for this afternoon. Downtime about 1/2 hour so far. 


-12:15pm- Excavator back down to begin rock breaking again. 

13:23pm- Rock border being put back along Flower bed and drive. 

14:08pm- Rock work and backfill coming along nicely!

14:19pm- Excavator back uptop. All rock broke for now until it can be hauled out. No more work here today to be done. 

15:08pm- Cutting clay from what was existing gravel before we dug here. 



15:40pm- Gravel going down now!

16:28pm- MH A02 riser and tapper rings are now placed. Vacuum testing to occur later in the week here and at A04. 

16:58pm- Tower Rd signage now back up. This concludes the day. 