Hwy 86 Sewer Ph 1
07:16am- Crew here will be making tie in at MH A04 today.
07:50am- Rock breaking continues here at Arena LS today.
09:20am- Force main now tied to MH A04.
09:48am- Now ready for thrust blocking.
10:15am- Saw cutting control joints now starting on driveway at Fire Dept.
10:40am- Thrust block now poured on fittings at tie in.
11:01am- Saw cuts nearly completed.
11:38am- Riser, ring and lid are on top of MH A04 now. Backfill begins.
11:50am- Changing out operator on breaking rock for this afternoon. Downtime about 1/2 hour so far.
-12:15pm- Excavator back down to begin rock breaking again.
13:23pm- Rock border being put back along Flower bed and drive.
14:08pm- Rock work and backfill coming along nicely!
14:19pm- Excavator back uptop. All rock broke for now until it can be hauled out. No more work here today to be done.
15:08pm- Cutting clay from what was existing gravel before we dug here.
15:40pm- Gravel going down now!
16:28pm- MH A02 riser and tapper rings are now placed. Vacuum testing to occur later in the week here and at A04.
16:58pm- Tower Rd signage now back up. This concludes the day.