Rock breaking for sump in LS will continue today until Noon. I will not be onsite today due to having my 40 hours in. This is a half day makeup for Operator.
07:19am- Another picture of floor in the AWWOB after it has dried out some. 07:24am- Rock breaking occurring this morning as we near the power line easement. 08:29am- 1st joint for today getting gravel! 08:55am- 2nd joint going in! 10:07am- Another joint goes in and the encasement will statt from this point. 12:00pm- 100’ now placed as cage begins around pipe within easement of power lines. 13:18pm- Cage is coming along as is the rock breaking! 13:41pm- Another joint placed and cage will continue! 16:14pm- Crew now has rebar tied and ready now for next joint now! 16:55pm- Crew has laid 160’ of pipe and built a cage for 60’ of it in the power line easement. This will conclude the day here.
Contractor started at 9:45am assembling newly acquired spools started to set valve assembly in vault. GRE employee did not have access to blogger, but took many pictures. Alignment of pipe so they can install a link seal Contractor continue with lining up valves in valve vault. Installing last link seal Contractor is done for the day
Contractor is excavating soil to install the air release/vacuum valve vault Flow meter valve installed Finish connecting for main lines 2:34pm air valve vault set 2:47pm flow meter tight, stands adjusted and torqued 3:30pm contractor tried installing stainless steel, intermediate rail, supports, and they were the wrong size, so remove them back out and started filling up ditch where force main comes out of wet well 5:30pm contractor filled in soil around volts won’t be back until Monday, depending on weather
Comments
Post a Comment