Hwy 86 Sewer Ph 1
07:12am- Excavator back onsite to continue rock breaking today.
08:04am- Excavator making way to wall of rock this morning.
08:54am- Progressing nicely this morning!
09:59am- Vacuum testing for MH A04 here and A 02 to occur today.
MH A04 doesn’t pass. Lid will need dug up.
10:30am- MH A02 passes vacuum test.
10:57am- MH A04 is getting dug up at this time.
11:50am- MH A04 now passes vacuum test.
12:22pm- Its starting to look like something now! Just a bit more rock breaking in upper left area of pic.

14:26pm- NE corner continues to be broke out as dozer begins pushing for the day.
14:26pm- NE corner continues to be broke out as dozer begins pushing for the day.
15:23pm- Orange dots with circles around them are subgrade essentially.
16:38pm- Just a bit more of broken rock to remove tomorrow and then they should break out sump pit in lift station.
This will round out their day here.