Hwy 86 Sewer Ph 1


07:12am- Excavator back onsite to continue rock breaking today. 

08:04am- Excavator making way to wall of rock this morning. 

08:54am- Progressing nicely this morning!


09:59am- Vacuum testing for MH A04 here and A 02 to occur today. 

MH A04 doesn’t pass. Lid will need dug up. 


10:30am- MH A02 passes vacuum test. 

10:57am- MH A04 is getting dug up at this time. 

11:50am- MH A04 now passes vacuum test. 
12:22pm- Its starting to look like something now! Just a bit more rock breaking in upper left area of pic. 

14:26pm- NE corner continues to be broke out as dozer begins pushing for the day. 



15:23pm- Orange dots with circles around them are subgrade essentially. 

16:38pm- Just a bit more of broken rock to remove tomorrow and then they should break out sump pit in lift station. 



This will round out their day here. 