Hwy 86 Sewer Ph 1



-07:00 to 9:00am: Met with Bryan Boyce to enter past two weeks of time into new Advantage Point system. Showed him job sites and went over project with him. 

09:00am- Arena LS site work continues today. Broken rock being excavated out and dozer pushing material away from pad site. 



10:51am- Removal of broken rock about 3/4 of the way done now. 



12:04pm- Crew laying out corners approximately for about another foot of material to come out. 

13:03pm- Over-digging has occurred to get the soft clay material out. Down to solid rock now. 

14:07pm- Almost cleaned out again after clay removal. 

14:38pm- Scott Bailey w/ FlatCreek came to site to shoot corners of walls for crew to see how much more needs cut back. This is NW corner of box at orange shirted guy. 

This is NE corner of box and a few more feet of rock needs to be removed both vertically and horizontally.
South West end is very near grade and South East corner needs a few more feet of rook to come out. 

14:47pm- This whole shelf has to come out where they are standing. 

16:45pm- This rounds out the day here. Excavator now be heading to the top. 