Hwy 86 Sewer Ph 1


07:00am- Driveway here will be poured today. 

Gauge still holding 10psi so line to be put on test today. 

07:10am- Work at Arena LS site to continue. 

07:22am- Concrete here getting started now!

08:09am- Ready for concrete!

08:48am- Testing done on concrete! Air 5%, slump 6”, Temperature 64*F. 

09:11am- Pour nearing completion. 

09:29am- Pour done and finish work follows. 
09:34am- FlatCreek onsite to start pumping up forcemain for hydrostatic test. 

09:59am- Not enough water feeding pump! Crew will meed water truck. 

11:15am- Now hooked water truck to try again. 

11:25am- Rock breaking occurring at LS site. Dozer continues to clean up area. 



13:02pm- Just bled a bunch of air from line and we are back to filling line just through hose and not the pump. 

14:53pm- We are at 168psi one one gauge and about 115psi on the other. I had them go past the required 150psi just to ensure we are over the 1.5 x operating pressure. 

15:52pm- Not much occurred today at LS site. Crew I believe left around 12:30pm. 

16:04pm- Concrete scoring is all thats left here now. 

16:52pm- Line has passed hydrostatic test!