07:04am- Crew will finish setting structure here at STA 28+25 and clean area up before moving on.
07:50am- Structure is now placed.
09:09- Gravel has been placed over pipe and backfill is underway.
09:51am- Crew now at STA 46+97 for 6” tie in.
11:10am- A 12” to 6” reducer to 6”valve with short piece of 6” ductile with blind flange is now installed. Plastic goes over assembly for now.
11:47am- Structure not onsite for this 6” valve. Crew will have to come back.
12:59pm- Back to in line valve structure at cabin, or STA 54+23 cutting it down to finish grade.
13:53pm- Structure is now cut and backfilling rest of the way occurs.
14:32pm- Lid to be put on here at the Fire Station.
14:48pm- I stopped lid placement - Lid will only be temporarily placed due to it not having Con- Shied in it!
15:57pm- A temporary piece of pipe going in over 6” tie in valve.
16:12pm- Fire Station concrete pad has been swept and cleaned up.
16:32pm- Parking lot here at Branson Cedars is swept and cleaned as gravel is getting placed in low areas. This will round out the day!