Hwy 86 Sewer Ph 1


07:04am- Crew will finish setting structure here at STA 28+25 and clean area up before moving on. 

07:50am- Structure is now placed. 


















09:09- Gravel has been placed over pipe and backfill is underway. 


















09:51am- Crew now at STA 46+97 for 6” tie in.










































11:10am- A 12” to 6” reducer to 6”valve with short piece of 6” ductile with blind flange is now installed. Plastic goes over assembly for now. 

11:47am- Structure not onsite for this 6” valve. Crew will have to come back. 


















12:59pm- Back to in line valve structure at cabin, or STA  54+23 cutting it down to finish grade. 


















13:53pm- Structure is now cut and backfilling rest of the way occurs. 

14:32pm- Lid to be put on here at the Fire Station. 
















14:48pm- I stopped lid placement - Lid will only be temporarily placed due to it not having Con- Shied in it!
















15:57pm- A temporary piece of pipe going in over 6” tie in valve. 
























16:12pm- Fire Station concrete pad has been swept and cleaned up. 















16:32pm- Parking lot here at Branson Cedars is swept and cleaned as gravel is getting placed in low areas. This will round out the day!