Hwy 86 Sewer Ph 1
Crew is back onsite today to begin installing valves!
08:07am- Valves have been unloaded now and crew will get them to their respective locations.
08:45am- Crew cutting pipe for valve placement at STA 54+23 approximately.
09:19am- Valve getting placed.
10:23am- Still working to get valve established.
11:36am- Valve now in place here at STA 54+23.
Crew cutting riser now to be placed over valve.
12:02pm- A look down Tower Rd from Devils Pool to existing Lift Station site. Complaint has come in about being able to see it now.
13:05pm- Structure now set on blocks with gravel going in now.
13:26pm- Valve placement to begin here next off Jones Spur at STA 28+25 roughly.
14:40pm- Section of pipe now cut out for valve placement.
17:02pm- Concrete structure is getting cut now to fit over pipe. This will round out the day here.
.