Hwy 86 Sewer Ph 1


Crew is back onsite today to begin installing valves!


















08:07am- Valves have been unloaded now and crew will get them to their respective locations. 


















08:45am- Crew cutting pipe for valve placement at STA 54+23 approximately. 


















09:19am- Valve getting placed.


















10:23am- Still working to get valve established. 


















11:36am- Valve now in place here at STA 54+23. 
Crew cutting riser now to be placed over valve. 





































12:02pm-  A look down Tower Rd from Devils Pool to existing Lift Station site. Complaint has come in about being able to see it now. 



















13:05pm- Structure now set on blocks with gravel going in now. 


















13:26pm- Valve placement to begin here next off Jones Spur at STA 28+25 roughly. 


















14:40pm- Section of pipe now cut out for valve placement. 


















15:30pm- Valve on pipe now with adjoining pipe being cut to length!

16:36pm- Line is back together!

17:02pm- Concrete structure is getting cut now to fit over pipe. This will round out the day here. 