Hwy 86 Sewer Ph 1
07:00am- crew is awaiting trench box arrival to unload it at Jones Spur. Backfill over line is caught up now.


08:39am- Trench box is being brought to site!
09:45- Back digging finally today from STA 49+15 roughly.
10:55am- 1st joint of the day!
11:38am- 2nd joint. Ditch has to curve to much for trench box…
12:52pm- 3rd joint placed.
13:36pm- 4th now placed.

14:42pm- 6th joint being checked to assure positive rise in pipe as they begin digging across dip in the ground.
15:24pm- 7th joint and we are in the bottom of the dip with 4+’ of cover at STA 50+56 roughly.

16:47pm- Pipe is now all bedded up to approximately STA 50+56 area.
22.5*fitting now gets installed near same location.
17:19pm- Crew is calling it a day. This 15’ section will be installed tomorrow morning to start the day. Approximately 250’ placed today.