Hwy 86 Sewer Ph 1


06:54am- Making our way to STA 48+05 where this long radius stops. Two slope anchors to be placed on the way to STA. 
























07:24am- 1st joint for today!
























08:29am- 40’ is placed as gravel goes in on pipe. 
























09:25am- 60’ in as more ditch is graveled for next joint. 
























10:18am- 80’ in place as excavator should start leveling out to maintain depth across slope to next transition up the hill. Should cross slope at about 12’ deep. 
























12:47pm- 100’ is laid and crew shoots grade for next dip in ground at STA 50+75 roughly to ensure they are deep enough now. 

























14:22pm- 160’ now placed as they approach STA 49+00. 
























16:17pm- Approximately 200’ of pipe placed. Crew will fall back and backfill. Trench box to arrive tomorrow hopefully. 