07:03am- Crew will begin today near STA 37+00, continuing to lat pipe to the east.
07:31am- Joint #1 begins the day!
8:13am- #2.
08:54am- 120’ now being placed.
09:50am- 160’.
10:49am- Pipe now at STA 39+20 roughly.
11:44am- 300’ !
12:49pm- 340’ going in now…
13:51pm- 380’ in.
14:32pm- Digging out for ARV structure now; of which is moved to the west six feet on stationing.
14;48pm- High Point is now established at ARV.
15:47pm- 500’ in now and Escobar says, “lay more pipe!”.
17:12pm- 520’ in now as the skidsteer threw a track and it had to be put back on-
17:25pm- Crew will gravel up this joint of pipe for a total today of 540’.