Hwy 86 Sewer Ph 1
06:59am- Rocks are being moved first thing this morning from path of line.
07:17am- Digging for end of casing on south side.
08:54am- Casing now exposed on south end.
09:22am- Spacer will be going onto gravity pipe today!
10:36am- Bore is now getting loaded!
11:53am- Unloading bore now due to a bell getting broke during installation.
12:47pm- 1st load of manholes have arrived!
13:37pm- Back loading bore.
14:24pm- Loading manholes now to haul to north side of bore.
15:12pm- Unloading manholes A1, A2, and A3 now for gravity section of line across from Fire Station.
16:20pm- Back loading Bore now.
17:16pm- Not enough spacers onsite for gravity line to continue, so excavation for electrical supply lines started, but ended due to lack of daylight.