Hwy 86 Sewer Ph 1


06:59am- Rocks are being moved first thing this morning from path of line. 


















07:17am- Digging for end of casing on south side. 


















08:54am- Casing now exposed on south end. 

09:22am- Spacer will be going onto gravity pipe today!

10:36am- Bore is now getting loaded!

11:53am- Unloading bore now due to a bell getting broke during installation. 


















12:47pm- 1st load of manholes have arrived!


















13:37pm- Back loading bore. 


















14:24pm- Loading manholes now to haul to north side of bore. 


















15:12pm- Unloading manholes A1, A2, and A3 now for gravity section of line across from Fire Station. 










































16:20pm- Back loading Bore now. 


















17:16pm- Not enough spacers onsite for gravity line to continue, so excavation for electrical supply lines started, but ended due to lack of daylight.