Hwy 86 Sewer Ph 1
07:14am- Rebar is cut to start on slope anchors this morning.
07:26am- 1st done.
08:32am- Last anchor being built while others are getting dug out by hand to remove some gravel.
09:10am- 1st joint of the day going in!
Soil trench seals are doing their job!
10:04am- STA 34+36 gets an 11.25* bend.
11:00am- Concrete for slope anchors begins.
11:32- All 5 now completed.
11:37am- 120’ now placed arriving at STA 35+00. We are off setting center line by 7’ to avoid trees to STA 37+00 roughly.
13:07pm- 160’ of pipe placed now.
14:25pm- 22.5* fitting going in at STA 35+95.
16:02pm- 260’ to STA 36+37 roughly.
16:40pm- Another 22.5* fitting going in at STA 36+58 now.
17:15pm- 300’ laid today! Gravel to follow.