Hwy 86 Sewer Ph 1
07:05am- Pavement will be cut today so line work can continue.
08:26am- 20’ of pipe placed now this morning.
9:50am- 40’ in place! All dirt is being hauled out as all fill will be clean rock from here on across lot.
12:01pm- 60’ in place and gravel fill will continue.
12:17pm- Out in roadway now, but traffic has a way around!
12:55pm- Path around work.
15:20pm- 80’ in place now.
16:39pm- 100’ now in place!
17:16pm- Crew is placing equipment around open trench for tonight.