Hwy 86 Sewer Ph 1
06:38am- Crew will continue to dig for utilities today and try and get around this cabin!
07:41am- 22.5* bend getting installed now.
08:30am- Power line is located as they will continue to dig around it.
10:02am- 25’ of pipe is placed now!
11:29am- A 22.5* bend is installed to get on around cabin!
11:59am- Now searching for main underground power from transformer cabinet.
14:29pm- Cable TV and Electric lines found with approximately 55’ of pipe now laid.
15:51pm- 75’ of pipe in now and past utilities at this time. Water lines may end up being an issue since no one knows exactly where they are!
Ditch tape also going in at this time so that backfill can be done to reach rest of pipe for graveling purposes.
17:35pm- 95’ today and the crew is finishing up!