Hwy 86 Sewer Ph 1


06:57am- Discussion occurs on getting around the cabin and the need to move the plug valve location to the south 20’ approximately to get it out from under the trees. 


















07:43am- 2nd joint going in so far this morning!


















08:54am- 4th joint placed as crew will now trade out excavators, bringing up smaller to dig around cabin. 
























10:20am- 120’ now placed. 
























11:31am- Plug valve location is dug at STA 54+23. 
























12:40pm- Digging for last joint of pipe before 45* bend. Tight quarters!


















13:34pm- 160’ of pipe placed as crew will now be digging for utility crossings. 




















15:20pm- One line located and dug under now. 2” electric line yet to come. 


















16:44pm- Rest of the force main has arrived and is now unloaded. 