Hwy 86 Sewer Ph 1
06:57am- Discussion occurs on getting around the cabin and the need to move the plug valve location to the south 20’ approximately to get it out from under the trees.
07:43am- 2nd joint going in so far this morning!
08:54am- 4th joint placed as crew will now trade out excavators, bringing up smaller to dig around cabin.
10:20am- 120’ now placed.
11:31am- Plug valve location is dug at STA 54+23.
12:40pm- Digging for last joint of pipe before 45* bend. Tight quarters!
13:34pm- 160’ of pipe placed as crew will now be digging for utility crossings.
15:20pm- One line located and dug under now. 2” electric line yet to come.
16:44pm- Rest of the force main has arrived and is now unloaded.