Hwy 86 Sewer Ph 1
07:27am- Crew will continue from near STA 30+00 today. Excavator down again this morning so smaller one to be used.
08:29am- 1st joint of the day getting gravel!
08:50am- Near STA 30+40 a trench seal will be installed to keep the ground water from following the trench!
09:48am- nearing bend at STA 30+93.
10:32am- A 22* bend is getting installed at STA 30+93.
11:03am- Fitting is near finished!
12:28pm- Roughly 160’ laid so far today.
13:20pm- 200’ now placed.
15:07pm- 300’ in place. Another trench seal will be placed due to the excessive ground water…
15:36pm- Running into what appears to be irrigation line at STA 33+00.
16:39pm- 360’ now placed.
17:03pm- 320’ laid today as crew will now dig test hole down closer to pond in easement to see if there is going to be ground water. If so they will bring pumps in the morning.
I will be headed offsite now.