Hwy 86 Sewer Ph 1
07:29am- Excavator has hit a footing for an old sign.
They will be digging it up before 1st joint of pipe can be laid for today.
08:20am- Footing is now out of the way and pipe is being laid!
09:33am- 120’ of pipe now laid!
10:15am- Crew looking at current depth and seeing if they will be approach casing correctly.
11:15am- 220’ of pipe in ditch now for today so far!
12:42pm- Excavator placing dirt on top of gravel and ditch tape before dozer begins backfill process.
13:18pm- Dozer begins backfilling over pipe. Fittings will be left open until concrete thrust blocks can be placed.
14:04pm- Now digging at casing so that ditch depth can be tied in appropriately.
16:10pm- Ditches are together now and two more pipes are laid. 22.5* fitting is placed for alignment. Crew will start installation of pipe through casing now.
16:52pm- Crew has laid 300’ of pipe today with an additional 40’ pushed into casing. More cleanup will round out the day.