Hwy 86 Sewer Ph 1
08:21am- Crew is back digging today at Jones Spur to continue laying pipe.
Rock is placed so that haul trucks quit tracking mud onto roadway.
10:12am- 22.5* bend installed!
10:56am- Pipe is graveled, except for 22.5 fitting. Ditch tape also installed. Crew will came back to fitting and concrete later today.
12:36pm- Another joint getting placed as ditch nears air release STA 26+42.60.
13:24pm- High point in pipe now established.
14:47pm- 45* fitting getting installed at STA 25+58.
15:54pm- Having crew keep an eye on the pipe with level to ensure no false high spot is created as they dig the ditch.
16:56pm- Last piece of pipe for the day with roughly 265’ laid today!