Hwy 86 Sewer Ph 1


08:21am- Crew is back digging today at Jones Spur to continue laying pipe. 


















Rock is placed so that haul trucks quit tracking mud onto roadway. 


















10:12am- 22.5* bend installed!

10:56am- Pipe is graveled, except for 22.5 fitting. Ditch tape also installed. Crew will came back to fitting and concrete later today. 

12:36pm- Another joint getting placed as ditch nears air release STA 26+42.60.

13:24pm- High point in pipe now established. 
14:47pm- 45* fitting getting installed at STA 25+58.

15:54pm- Having crew keep an eye on the pipe with level to ensure no false high spot is created as they dig the ditch. 

16:56pm- Last piece of pipe for the day with roughly 265’ laid today!