Hwy 86 Sewer Ph 1
07:20am- Pipe will be unloaded while casing is getting finished up with welding this morning.
07:50am- After measuring the casing, an additional piece is needed to get to the required footage of 127’.
09:19am- Casing nears edge of ditch.
09:36am-ThunderRidge casing is placed and gravel backfill begins.
10:21am- Work will resume here at Jones Spur once clearing of trees is finished.
11:36am- Rains begin as another truck load of pipe arrives.
-1:51pm- Crew will not be working rest of the day do to rain.