Hwy 86 Sewer Ph 1
Crew did not work yesterday the 30th, due to ground being too wet from rains over the weekend.
Today a plug valve will be set very near STA 28+00 to begin new section of line to the east of Jones Spur.
07:42am- Crew will now just continue joining pipe from this point due to the plug valves not being onsite and are back ordered.
The line is full of water , so this could be interesting…
07:50am- Bleed off begins!
09:11am- 1st joint heading east now placed.
10:38am- Excavator issues again. 3rd joint now placed with area left open for slope anchor.
11:52am- 4th joint in.
13:08pm- 5th joint.
14:31pm- 7 joints placed with Mr. Escobar stopping by.
14:56pm- A look from the bottom of the hill back up.
16:01pm- Domed lateral field found from old drain possibly from pond…?
17:13pm- Tree roots are getting cut back.
17:19pm- Last joint of pipe for today going in. 200’ today roughly.