Hwy 86 Sewer Ph 1
07:27am- Excavator continues to backfill this morning as cleanup occurs all over job site today. If all goes well, line testing may occur. 
08:31am- Thrust block at 11.25* fitting is underway near STA 3+56.

09:34am- Excavator cutting road path in from STA 28+00 headed east, so that pipe can be taken into site

13:16pm- Spoil cleanup along Thunder Ridge still occurring.

16:35pm- Well, never even got up to pressure. Only about 50 psi.
08:31am- Thrust block at 11.25* fitting is underway near STA 3+56.

09:34am- Excavator cutting road path in from STA 28+00 headed east, so that pipe can be taken into site

10:28am- Trees are starting to come down.
11:13am- Last bit of brush from tree leaving now.
11:28am- Awaiting Blue Green to approve this tree removal.
13:16pm- Spoil cleanup along Thunder Ridge still occurring.
14:11pm- Pipe is getting strung out down the fairway now.
14:59pm- Written approval from BlueGreen is now on file for tree removals.

16:13pm- Hydrostatic testing to begin!
16:35pm- Well, never even got up to pressure. Only about 50 psi.
17:07pm- Cap moved and pipe also pulled from gasket joint 19’ back.
17:39pm- Crew will return in the morning and remove last joint, re-dig ditch and install cap again with better thrust blocks.