Hwy 86 Sewer Ph 1
08:58am- Crew has laid 60’ of pipe this morning while I was picking up my new iPhone from the Springfield Office.
10:33am- I spoke with Engineer and I’m have contractor to continue with the current pipe radius to skip turn at STA 0+52 and stop at 0+45 eliminating the fitting.
11:48am- 120’ of pipe now laid in place.

13:31pm- Last joint of pipe for this end getting ready to go in. Pipe will be at STA 0+45 roughly.
14:06pm- Cap is now on end of pipe!
14:48pm- Lune is now getting filled from ARV location 3+56ish.
14:57pm- Line taped at STA 26+42 for other ARV!
15:20pm- Putting cap on end of pipe at Jones Spur at STA 28+00.
16:55pm- Water still going in at STA 3+56.
17:16pm- Backfill of area still continues!

Filling the line will continue tonight. I will be headed offsite now.