Hwy 86 Sewer Ph 1
07:48am- Crew is cutting the roadway this morning.
09:16am- Still cutting roadway.
09:43am- Pipe is now out in the road.
09:52am- Thrust blocks are getting poured from STA 7+00 back to STA 14+62 area.

11:11am- Halfway across road now with street plate in place.
12:41pm- Across roadway and headed to ARV location at STA 3+41.

13:34pm- Pipe is at ARV location now.
14:09pm- 11.25* bend @ 50’ from west side of pavement.
17:09pm- Approximately 250’ laid today arriving at STA 2+25 roughly.