Hwy 86 Sewer Ph 1






























07:20am- After moving some of their supplies out of the way; the crew is back to digging towards STA 4+25 at roadway from STA 6+50. 



















09:47am- Pipe now laid up to STA 5+40 approximately and spotting of utilities now occurring.

10;40am- Utilities are located!


















11:45am- Crossing of the utilities is next! STA 5+00 is in 20’. 


















13:09pm- Still digging to get through utilities!


















14:14pm- Pipe is now laid past buried utilities. 
(electric & fiber)




































15:23pm- Trackhoe went down again about 50’ from roadway…  gravel backfill now occurs in roadway. 


















17:11pm- Pipe laying has brought us to STA 4+25 approximately today. Gravel backfill will round out the day. 225’ of pipe today roughly. 










 