Hwy 86 Sewer Ph 1

7:06am- Pipe work will pick up today from near STA 9+60.

08:37am- Digging now at STA 8+50. 80’ of pipe laud thus far today!

10:25am- Nearing STA 7+50. 




















11:06am- Officially at STA 7+50 now. Crew will fall back and gravel backfill until we hear something to move forward with change order from Big Crdar. 


















11:32am- Gravel bedding backfill occurring!


















12:42pm- Pipe is bedded and 2” clean will cap it off for now. 


















14:12pm- Digging begins from STA 7+50 now to head to STA 4+25 approximately keeping to the east side of the current entry road to Shooting Academy. 


















15:42pm- 30’ of pipe now placed in ditch from STA 7+50. 




















16:55pm- Gravel bedding will round out the day here at STA 6+50. Approximately 320’ laid today. 