Hwy 86 Sewer Ph 1
07:11am- Teeth on excavator is getting changed out first thing this morning.
09:59am- Boot is placed on east end of casing under Thunder Ridge Rd.

8:12am- Pipe on east end of casing being tied in.
09:04am- 45* Fitting at STA 12+57.
09:34am- Gravel backfill begins.
09:59am- Boot is placed on east end of casing under Thunder Ridge Rd.
10:03am- Ditch tape goes in.
10:08am- Rip Rap is placed over the 3’ of gravel placed on line.
10:40am- Rip Rap is placed and dirt will now go over it.

11:13am- West end of pipe at casing gets the 11.25* fitting placed.
11:23am- Issue with the excavator. Mechanic is on the way to look at it.
12:40pm- Large excavator still down, but we are back to digging with smaller one!
13:29pm- Pipe is now getting tied to the 11.25* fitting.
14:56pm- Two joints now west of casing. Digging for 22.5* turn at STA 10+00.
15:51pm- 22.5* turn is now installed on pipe at STA 10+00.
17:16pm- Pipe is bedded and gravel backfill going in to round out the day. Around 150’ of pipe laid today due to issues with the larger trackhoe.