Hwy 86 Sewer Ph 1

07:11am- Teeth on excavator is getting changed out first thing this morning. 




















8:12am- Pipe on east end of casing being tied in. 

























09:04am- 45* Fitting at STA 12+57. 



















09:34am- Gravel backfill begins. 


















09:59am- Boot is placed on east end of casing under Thunder Ridge Rd. 


















10:03am- Ditch tape goes in. 


















10:08am- Rip Rap is placed over the 3’ of gravel placed on line. 


















10:40am- Rip Rap is placed and dirt will now go over it. 



















11:13am- West end of pipe at casing gets the 11.25* fitting placed. 


















11:23am- Issue with the excavator. Mechanic is on the way to look at it. 


















12:40pm- Large excavator still down, but we are back to digging with smaller one!


















13:29pm- Pipe is now getting tied to the 11.25* fitting. 


















14:56pm- Two joints now west of casing. Digging for 22.5* turn at STA 10+00. 


















15:51pm- 22.5* turn is now installed on pipe at STA 10+00. 



















17:16pm- Pipe is bedded and gravel backfill going in to round out the day. Around 150’ of pipe laid today due to issues with the larger trackhoe. 