Hwy 86 Sewer Ph 1
07:08am- Pipe work continues this morning near STA 14+61.
Mr. Escobar worked Friday to do cleanup along line.
08:18am- 1st full joint for the day!
09:38am- 3rd full joint of the day!
11:21am- 5th joint with a 11.25* fitting installed near STA 14+14.
12:45pm- Pipe is now to STA 13+00.
14:00pm- Ditch is dug onto the 45*turn and onto casing!
14:33pm- Old culvert hit. I had ESS and Ownership out to see it. Everyone agrees to abandon it.
15:25pm- Crew leaves East end ditch open to begin loading casing from West end.
17:06pm- Casing is now loaded!
17:30pm-Approximately 370’ of pipe placed today.