Hwy 86 Sewer Ph 1
































07:08am- Pipe work continues this morning near STA 14+61. 


















Mr. Escobar worked Friday to do cleanup along line. 


















08:18am-  1st full joint for the day!


















09:38am- 3rd full joint of the day!


















11:21am- 5th joint with a 11.25* fitting installed near STA 14+14. 


















12:45pm- Pipe is now to STA 13+00. 


















14:00pm- Ditch is dug onto the 45*turn and onto casing!


















14:33pm- Old culvert hit. I had ESS and Ownership out to see it. Everyone agrees to abandon it. 


































15:25pm- Crew leaves East end ditch open to begin loading casing from West end. 


















17:06pm- Casing is now loaded!


















17:30pm-Approximately 370’ of pipe placed today. 