Hwy 86 Sewer Ph 1
07:05am- Pipe work continues today as they approach STA 16+52.
07:35am- Excavator stopped digging and moved to Thunder Ridge to backfill slope over casing so clean rock can be dumped in roadway today.
09:03am- Crew is now installing the 22.5* fitting at STA 16+52.
10:09am- 60’ laid now so far today.
11:07am- Approximately 112’ of pipe laid now.
13:50pm- Concrete finally arrives and fitting from Jones Spur to STA 16+52 get thrust blocks poured. (8 total finngs)

14:24pm- Gravel then covers thrust blocks and rest of pipe so backfill can continue.
14:57pm- Crew prepares to set 22.5* fitting here at STA 14+61.
16:11pm- Fitting if now set and attached to pipe. Crew is stopping here to go up and finish off filling roadway over casing on Thunder Ridge Rd.
16:48pm- Crew will finish up their day here. Approximately 230’ of pipe laid today.