Hwy 86 Sewer Ph 1



07:05am- Pipe work continues today as they approach STA 16+52.
 









































07:35am- Excavator stopped digging and moved to Thunder Ridge to backfill slope over casing so clean rock can be dumped in roadway today. 


















09:03am- Crew is now installing the 22.5* fitting at STA  16+52.


















10:09am- 60’ laid now so far today. 


















11:07am- Approximately 112’ of pipe laid now. 


















13:50pm- Concrete finally arrives and fitting from Jones Spur to STA 16+52 get thrust blocks poured. (8 total finngs)



































































14:24pm- Gravel then covers thrust blocks and rest of pipe so backfill can continue. 


















14:57pm- Crew prepares to set 22.5* fitting here at STA 14+61. 


















16:11pm- Fitting if now set and attached to pipe. Crew is stopping here to go up and finish off filling roadway over casing on Thunder Ridge Rd. 


















16:48pm- Crew will finish up their day here. Approximately 230’ of pipe laid today. 