Hwy 86 Sewer Ph 1
07:07am- 22.5* fitting going in at STA 18+84 this morning.
08:50am- Two joints of pipe laid now. Crew will fall back and backfill.
09:56am- Gravel backfill in roadway continues!
11:19am- Another 22.5* bend installed and crew is now at STA 18+23 roughly.
13:48pm- Pipe is nearing STA 17+37 now. No 11.25* fitting used at STA 17+76 area.
15:40pm- An 11.25* fitting used and pipe is now to approximately STA 17+12.
16:18pm- With approximately 210’ of pipe laid for today, crew will stop and gravel all the pipe now and continue with backfill.